|
Progress at Cameron LNG
Nearly a year since construction began at
the 275-acre, industrially zoned site
along the Calcasieu Ship Channel, Cameron
LNG's receipt terminal is on a steady course
toward completion, despite Hurricane Rita's
fury last September.

Once completed, Cameron LNG's three natural gas storage tanks will stand about 18 stories tall.
|
With approximately 250 workers and a
five-day work-week schedule starting at
7 a.m. and ending around 5 p.m., the
project is
20 percent complete and on
schedule.
Construction site manager Alan Zachary
and his staff oversee the development of the
Cameron LNG project. "It is our responsibility
to look after Sempra LNG's interest and to
ensure the facility is constructed in accordance
with all permits and contractual specifications,"
explains Zachary.
Aker Kvaerner/IHI (AK/IHI) serves as the
project's engineering, procurement
and construction contractor and
manages both the construction and
the subcontractors working on the
terminal. "We work hand-in-hand
with AK/IHI and their very dedicated
management team," says Zachary.
"The progress on this terminal has
been amazing."
Traveling along Highway 27, the
construction efforts can be seen as the
terminal site is built into a state-ofthe-
art facility. About 1,450 concrete
pilings were placed 90 feet below
ground to form the base of each of
the three tanks that will store minus-260 degree Fahrenheit liquefied
natural gas.
Dredging the berth area where LNG
tankers will offload is scheduled to
begin this month and will be
completed by mid-February next year.
Once complete, nearly 45 feet of
dredged material will have been
removed from the 2,000-foot-wide
area, providing the needed space for
two unloading docks.
Possible traffic delays
Safety is a top priority at the
Cameron LNG site, and keeping the
public aware of major construction
events and potential traffic delays is
important to Zachary and his team.
"Communication with the community
is key," says Zachary. "Our commitment
is to make sure the public is
aware of our busiest construction
times and when we'll have a lot of
traffic coming and going from the
site's plant entrance so that we can
keep everyone safe on Highway 27."
The busiest times at the site
entrance are around 7 a.m. and
5 p.m., so expect potential traffic
delays near these hours. It is also
the project team's intent to notify
the public when major deliveries
are scheduled that could potentially
pose traffic delays.

|